FERNAS CONSTRUCTION COMPANY INC VS. GUJARAT STATE PETRONET LTD. [GUJARAT HIGH COURT, 212016]

October 24, 2016

In Fernas Construction Company Inc vs Gujarat State Petronet Ltd, the Gujarat High Court examined whether an interim injunction under Section 9 of the Arbitration and Conciliation Act 1996 can restrain the encashment of unconditional bank guarantees. The Court reaffirmed that encashment of unconditional bank guarantees cannot be stayed absent established egregious fraud or irretrievable injustice.

Case Overview and Procedural Background

The petitioner, Fernas Construction Company Inc, a company incorporated in Turkey, filed an application under Section 9 of the Arbitration and Conciliation Act 1996 read with provisions of the Commercial Courts Act 2015 before the High Court of Gujarat (Coram: Hon'ble Mr. Justice R.M. Chhaya). The petitioner sought an interim injunction restraining respondent No. 1, Gujarat State Petronet Ltd (GSPL), a public sector enterprise of the State of Gujarat, from invoking and encashing two bank guarantees issued by Axis Bank:

  • Advance Bank Guarantee: Bank Guarantee No. 1609FBG130018 dated 29.01.2013 for Rs. 7.50 Crores, valid up to 31.12.2016.
  • Performance Bank Guarantee: Bank Guarantee No. 1609FBG130009 dated 11.01.2013 for Rs. 27,29,69,140, valid up to 31.12.2018.

Prior to filing the Section 9 petition, the petitioner had preferred a writ petition under Article 226 of the Constitution of India (Special Civil Application No. 13640 of 2016). The learned Single Judge dismissed the writ petition on 04.10.2016 on grounds of alternative statutory remedy. A subsequent Letters Patent Appeal (LPA No. 995 of 2016) was dismissed by the Division Bench on 05.10.2016, leading the petitioner to invoke Section 9 for interim protective relief.

Factual Matrix and Contractual Dispute

Respondent No. 1 awarded a construction contract to the petitioner vide Letter of Intent dated 20.09.2012 for the execution of a Gas Compressor Station in Gujarat. The contract stipulated a completion period of 17 months, comprising 15 months for engineering, procurement, and construction, and 2 months for testing and commissioning. Time extensions were granted up to 31.08.2016. On 09.08.2016, respondent No. 1 terminated the contract alleging substantial non-performance and project delays. By the date of the hearing, the Advance Bank Guarantee of Rs. 7.50 Crores had already been encashed, leaving the dispute centered on the Performance Bank Guarantee of Rs. 27.29 Crores.

Submissions of the Petitioner

Senior Counsel for the petitioner argued that the petitioner had achieved 63 percent completion and that the termination was premature and wrongful. The primary contentions included:

  • Requirement of an Adjudicated Claim: Even though the bank guarantee was unconditional on its face, the right to invoke performance security was qualified by the General Conditions of Contract. It was contended that an unadjudicated claim for unliquidated damages could not justify encashment.
  • Contractual Ceiling on Damages: Relying on contractual clauses, the petitioner contended that liquidated damages were subject to a maximum ceiling of 10 percent of the contract value, which was already covered by retained amounts.
  • Reliance on Gangotri Enterprises: Counsel placed heavy reliance on the Supreme Court judgment in Gangotri Enterprises Ltd. v. Union of India (Civil Appeal No. 4814 of 2016), asserting that interim relief should be granted to prevent wrongful encashment.

Foundational principles of contractual obligations and breach are detailed in contract law study notes on performance and breach, illustrating how underlying disputes relate to commercial commitments.

Submissions of Respondent No. 1: Autonomy of Bank Guarantees

Senior Counsel appearing for Gujarat State Petronet Ltd resisted the petition on both preliminary and substantive grounds:

  • Res Judicata and Prior Findings: The identical reliefs and arguments concerning bank guarantee encashment had been considered and rejected in the earlier writ petition and Division Bench appeal.
  • Independent Contractual Obligation: An unconditional bank guarantee constitutes an independent contract between the issuing bank and the beneficiary. The beneficiary is entitled to realize the guarantee upon demand without proving default or loss in a prior arbitration.
  • Distinction of Gangotri Enterprises: In Gangotri Enterprises, the bank guarantee related to a completed contract with no outstanding claims, whereas the Railways sought encashment for an entirely different contract. In the present case, the bank guarantee was issued specifically for performance of the subject Gas Compressor Station contract.

For a detailed analysis of commercial instruments and guarantees, see the banking law class notes on bank guarantees covering statutory rights of beneficiaries and issuing banks.

Judicial Precedents on Restraining Bank Guarantee Encashment

The High Court reviewed established Supreme Court authorities governing bank guarantees:

  • U.P. State Sugar Corp. v. Sumac International Ltd. (1997) 1 SCC 568: Courts must not interfere with the encashment of unconditional bank guarantees except in cases of clear fraud of an egregious nature or irretrievable injustice.
  • Himadri Chemicals Industries Ltd. v. Coal Tar Refining Co. (2007) 8 SCC 110: Established six guiding principles, holding that commitments of banks must be honored free from judicial interference unless fraud or exceptional hardship is established.
  • Vinitec Electronics Pvt. Ltd. v. HCL Infosystems Ltd. (2008) 11 SCC 544: Reaffirmed that contractual disputes between the principal and beneficiary do not constitute fraud or justify staying encashment of unconditional guarantees.
  • Gujarat Maritime Board v. Larsen and Toubro (Civil Appeal No. 9821 of 2016): Confirmed that bank guarantee encashment is independent of underlying disputes between the contracting parties.

High Court Findings and Decision

The Gujarat High Court held that the Performance Bank Guarantee was an unconditional and irrevocable undertaking given by Axis Bank to pay Gujarat State Petronet Ltd on demand. The petitioner failed to plead or establish fraud of an egregious nature that would vitiate the entire underlying transaction. Furthermore, the financial difficulty of an overseas contractor having no local assets does not constitute irretrievable injustice of the kind recognized in law. The Court held that commercial arbitral disputes regarding delay, measurement, and wrongful termination must be decided on merits in arbitration proceedings, without restraining the beneficiary from encashing performance securities. The Section 9 petition was accordingly dismissed.

Key Takeaways for Commercial Arbitration

  1. Autonomous Character: Unconditional bank guarantees operate independently of disputes arising under the primary commercial contract.
  2. High Threshold for Injunctions: Courts will grant interim injunctions under Section 9 only upon proof of established fraud known to the bank or demonstrated irretrievable harm.
  3. Post-Encashment Arbitral Remedy: Any wrongful encashment can be remedied by an award of restitution and damages in final arbitration proceedings.

Found this helpful?

Share this page with others